I'm currently using MSP2003. Is there a way I can see the duration/remaining duration of a task in the Resource Usage View? Thanks!

Re: Duration in Resource View by Steve

Steve
Fri Aug 06 07:56:49 CDT 2004

In the task usage view you can but not in the resource usage view. Sorry


--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Deluth" <deluth@discussions.microsoft.com> wrote in message
news:B95988C6-FC76-4909-8FFE-B606508E47D4@microsoft.com...
> I'm currently using MSP2003. Is there a way I can see the
duration/remaining duration of a task in the Resource Usage View? Thanks!