I need to put a diferent percent for a resource in the same taks.
Example:( Task _ Planning - Resource - Fernando Gomes. Duration -
01/03/20008 to 30/04/2008 - March - Fernando Gomes 45% allocation - Apbril -
Fernando Gomes 75% allocation).

Re: Diferent percents for one resource in the task(Jan 50%, Feb 15%) by Jan

Jan
Thu Mar 13 10:44:25 CDT 2008

Hi,

Task usage View.
Put Month as minor timescale
Show the line percent allocation on the right (Right click, if percent
allocation is not visible Detail Styles, Percent allocation, show)

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Fernando Gomes" <Fernando Gomes@discussions.microsoft.com> wrote in message
news:F2FD985A-4874-46D6-BCFB-47BCAAD1C0A6@microsoft.com...
>I need to put a diferent percent for a resource in the same taks.
> Example:( Task _ Planning - Resource - Fernando Gomes. Duration -
> 01/03/20008 to 30/04/2008 - March - Fernando Gomes 45% allocation -
> Apbril -
> Fernando Gomes 75% allocation).



Re: Diferent percents for one resource in the task(Jan 50%, Feb 15 by Andy

Andy
Mon Apr 21 04:38:01 CDT 2008

I wish to alter my project 2003 plan in much the same way as Fernando does.
I have tasks where the resource allocation during the life of a single task
will alter over time (e.g. 100% from 28/10 till 04/11 then 50%). I have
followed your instructions in the reply, however upon viewing the Task Usage
information I cannot alter the percentage allocation already attributed
within my plan. How do I achieve this?

"Jan De Messemaeker" wrote:

> Hi,
>
> Task usage View.
> Put Month as minor timescale
> Show the line percent allocation on the right (Right click, if percent
> allocation is not visible Detail Styles, Percent allocation, show)
>
> Hope this helps,
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> +32 495 300 620
> For availability check:
> http://users.online.be/prom-ade/Calendar.pdf
> "Fernando Gomes" <Fernando Gomes@discussions.microsoft.com> wrote in message
> news:F2FD985A-4874-46D6-BCFB-47BCAAD1C0A6@microsoft.com...
> >I need to put a diferent percent for a resource in the same taks.
> > Example:( Task _ Planning - Resource - Fernando Gomes. Duration -
> > 01/03/20008 to 30/04/2008 - March - Fernando Gomes 45% allocation -
> > Apbril -
> > Fernando Gomes 75% allocation).
>
>
>

Re: Diferent percents for one resource in the task(Jan 50%, Feb 15 by Mike

Mike
Mon Apr 21 05:34:26 CDT 2008

Hi Andy,

Welcome to this Microsoft Project newsgroup :)

Jan is on holiday at the moment. Try this: View the Resource Sheet and
double click on the resource name. In the resource Information dialog,
click in the next space in the Resource Availability section and enter the
appropriate details.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #28 minimizing the effect of delays where this
procedure is itemized, at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials


Andy Wall wrote:
> I wish to alter my project 2003 plan in much the same way as Fernando
> does. I have tasks where the resource allocation during the life of a
> single task will alter over time (e.g. 100% from 28/10 till 04/11
> then 50%). I have followed your instructions in the reply, however
> upon viewing the Task Usage information I cannot alter the percentage
> allocation already attributed within my plan. How do I achieve this?
>
> "Jan De Messemaeker" wrote:
>
>> Hi,
>>
>> Task usage View.
>> Put Month as minor timescale
>> Show the line percent allocation on the right (Right click, if
>> percent allocation is not visible Detail Styles, Percent allocation,
>> show)
>>
>> Hope this helps,
>>
>> --
>> Jan De Messemaeker
>> Microsoft Project Most Valuable Professional
>> +32 495 300 620
>> For availability check:
>> http://users.online.be/prom-ade/Calendar.pdf
>> "Fernando Gomes" <Fernando Gomes@discussions.microsoft.com> wrote in
>> message news:F2FD985A-4874-46D6-BCFB-47BCAAD1C0A6@microsoft.com...
>>> I need to put a diferent percent for a resource in the same taks.
>>> Example:( Task _ Planning - Resource - Fernando Gomes. Duration -
>>> 01/03/20008 to 30/04/2008 - March - Fernando Gomes 45% allocation -
>>> Apbril -
>>> Fernando Gomes 75% allocation).