I have a problem of clarity in MS Project Pro 2007. Dependency links are
shown to the Baseline Bar symbols and not to the current Task Bar. I feel
certain that this is not as nature (and Microsoft ;-) intended. I should
like to find a remedy for this before I transfer the programmes into my
Client's Project Server EPM system

I have known the problem in v.2003, but not quite as seriously.

Re: Dependency links to Baseline Dates by Jack

Jack
Mon Nov 12 09:35:49 PST 2007

Make sure that your baseline bar style is not the first one in the list.
Go to format menu, select barstyles, then move the baseline style further
down.

-Jack Dahlgren

"Jim Trickett" <JimTrickett@discussions.microsoft.com> wrote in message
news:06CDCB3F-85CE-4527-9193-77845E7EB95F@microsoft.com...
>I have a problem of clarity in MS Project Pro 2007. Dependency links are
> shown to the Baseline Bar symbols and not to the current Task Bar. I feel
> certain that this is not as nature (and Microsoft ;-) intended. I should
> like to find a remedy for this before I transfer the programmes into my
> Client's Project Server EPM system
>
> I have known the problem in v.2003, but not quite as seriously.