I am working on a project in which I need to provide dates to the same
recurring set of tasks for different classes. The dates need to be a week
before training delivery or 2 weeks before 4 weeks before etc. Is there some
way that I can customize the task to provide dates in this fashion?
--
Gina

Re: Date help by JulieS

JulieS
Fri Jun 15 11:40:43 CDT 2007

Hello Gina,

Have you tried a start to start link with a lead between the training
delivery task and the other tasks?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"Gina" <Gina@discussions.microsoft.com> wrote in message
news:B85EB2BD-00B9-4D71-A07A-ABDA8F17A7E4@microsoft.com...
>I am working on a project in which I need to provide dates to the same
> recurring set of tasks for different classes. The dates need to be a
> week
> before training delivery or 2 weeks before 4 weeks before etc. Is
> there some
> way that I can customize the task to provide dates in this fashion?
> --
> Gina