JimAksel
Wed May 23 16:32:00 CDT 2007
A custom field such as Cost1 or Text1 works just fine.
Insert a Cost1 field (column). Right click on it.
Select Customize Fields
Select Formula
70*[Acutal Work]/60
Why the 60? Work is stored in minutes by MS Project, it may be displayed
differently but is stored in minutes. So, a conversion is needed and will
change depending on the units displayed in the Actual Work column. A more
robust solution would be possible if you tested on the units for display and
then picked your coversion accordingly.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project
"Bud" wrote:
> I created a custom field for Revenue.
>
> It's a simple calculation of 70*Actual_Work. However, actual work has the
> hrs designator in their so in order for this calculation to be correct I have
> to use another field and take the hrs designator out of the field.
>
> Is there any way to use Actual work the way it is with the hrs designator in
> their with the formula. I don't want to have to create a whole new field than
> remove the hrs designator for this simple calculation.
>
> Thanks