"zelks" <zridjosic@hotmail.com> wrote in message
news:a50b9327-c1c6-4c32-befb-f70e10d7b2e5@c19g2000prf.googlegroups.com...
> Hello!
> I am trying to display critical path that lists tasks and deliverables
> by dates (the order in which they should occur rather than by
> phases). I have purchased the WBS Chart Pro but again, it even then,
> the tasks don't occur in order by dates but are organized by phases.
> Is there a way I can change that setting?
> Any advice would be much appreciated!
> ZR
Hello zelks,
I assume you are asking to sort a project file by start date of tasks
rather than by the start date of a phase. Try Project > Sort > Sort By.
For the first sort order select Start and uncheck the option at the
bottom of the dialog "Keep outline structure".
You may also find it helpful to show multiple critical paths. That
option is enable on the Calculation tab of the Tools > Options dialog
box.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project