Is there that a milestone can automatically be shown as critical on the Gantt
Chart, if the milestone shows a negative total slack?
Thanx
--
Regards
Tracey

Re: Critical Milestones by Trevor

Trevor
Fri Apr 21 05:34:06 CDT 2006

In the default Gantt Chart View, where the bar formatting is kept,
Milestones display as black even if they are Critical (Total Slack <= 0),
and even if you have run the Gantt Chart Wizard to show Critical Tasks.
Suggestion: leave the default Gantt Chart as it is, make a copy of it (View,
More Views etc), with a distinctive name like "AAA special Gantt Chart
number 1", and format its bar styles (Format, Bar Styles). Go down the list
to the black diamond for the Milestones and add another row below that.
Define the style, Name = Critical Milestone, definition is
"Milestone,Critical".

Trevor


"Tracey" <Tracey@discussions.microsoft.com> wrote in message
news:EF109B83-BABD-470A-8F07-FC32E2761E3B@microsoft.com...
> Is there that a milestone can automatically be shown as critical on the
> Gantt
> Chart, if the milestone shows a negative total slack?
> Thanx
> --
> Regards
> Tracey



Re: Critical Milestones by Tracey

Tracey
Fri Apr 21 08:04:02 CDT 2006

Thanx so much!
--
Regards
Tracey


"Trevor Rabey" wrote:

> In the default Gantt Chart View, where the bar formatting is kept,
> Milestones display as black even if they are Critical (Total Slack <= 0),
> and even if you have run the Gantt Chart Wizard to show Critical Tasks.
> Suggestion: leave the default Gantt Chart as it is, make a copy of it (View,
> More Views etc), with a distinctive name like "AAA special Gantt Chart
> number 1", and format its bar styles (Format, Bar Styles). Go down the list
> to the black diamond for the Milestones and add another row below that.
> Define the style, Name = Critical Milestone, definition is
> "Milestone,Critical".
>
> Trevor
>
>
> "Tracey" <Tracey@discussions.microsoft.com> wrote in message
> news:EF109B83-BABD-470A-8F07-FC32E2761E3B@microsoft.com...
> > Is there that a milestone can automatically be shown as critical on the
> > Gantt
> > Chart, if the milestone shows a negative total slack?
> > Thanx
> > --
> > Regards
> > Tracey
>
>
>