Re: Create a "Custom" Field by John
John
Mon Jan 16 10:56:32 CST 2006
In article <D6A11EA1-54BE-4369-B488-346DCCA4B6D3@microsoft.com>,
"(Charles Ray) cray@spiritconstruction.co"
<CharlesRaycrayspiritconstructionco@discussions.microsoft.com> wrote:
> John,
>
> Thanks so much for your help. I have been out of town on business and just
> noticed your reply.
>
> Thanks again,
>
> Charles
Charles,
Yeah, I wondered what happened to you. Glad we could be of help.
John
>
> "John" wrote:
>
> > In article <798C849D-1587-49A2-8EAC-84775EC7EB50@microsoft.com>,
> > "(Charles Ray) cray@spiritconstruction.co"
> > <CharlesRaycrayspiritconstructionco@discussions.microsoft.com> wrote:
> >
> > > How can I create a custom field that will show the "Projected % Complete"
> > > based on the current status date. I want to be able to compare the
> > > actual %
> > > complete with where it should be. I would also like to be able to show
> > > in a
> > > custom field the "current complete through date" for a task. This would
> > > be
> > > very useful in understanding a Late Task. This will be a visual aid for
> > > my
> > > customers that greatly speeds our project reviews. Your help will be
> > > greatly
> > > appreciated.
> > >
> > > I'm looking for a way to show where a
> > > % complete should be on the status date. If the task is late, and shows
> > > 33%
> > > complete, but on the status date it should be 41% complete I want to be
> > > able
> > > to show that as well as the "Complete Through Date" this will give a
> > > visual
> > > reference. Hypothetically - a task is 33% complete with a complete
> > > through
> > > date od 12/30/05, but on 1/10/06 the status date, it should have been 41%
> > > complete. I want to show in 2 separate columns 41% and 12/30/05.
> >
> > Charles,
> > In your original post on the developer newsgroup I suggested you
> > consider using standard classical earned value metrics. You never
> > indicated why that approach would not work.
> >
> > It is possible to pretty much generate any custom data desired either
> > through formulas in custom fields or if that doesn't work, definitely
> > with VBA. In the case of what you want, I can envision a formula in a
> > custom field that calculates the "projected % complete" value. The
> > formula might look something like:
> > Proj % Comp = ProjDateDiff([start],[status date])/[duration] x 100%
> >
> > It's not real clear what you mean by, "complete through date". If I
> > assume that is the equivalent date for the "normal" progress based on
> > the entered % complete value, then a similar formula (using ProjDateAdd)
> > to generate a date based on the % complete be used.
> >
> > John
> > Project MVP
> >