Steve
Tue Jul 26 16:50:20 CDT 2005
The "cost per use" is a fixed cost that will be charged you budget each time
the resource is assigned. The behaviour is the same whether we're talking
about a material resource or a work resource. For materials, I have a
resource that costs $10 standard rate and $5.00 per use and assign that
resource to one task for that uses 5 units, my cost is $10/unit * 5 units +
$5/use for a total of $55. If I assign the same resource to 5 tasks that
use 1 unit each, my cost is $10/unit * 1 unit/task * 5 tasks + $5.00/use * 5
uses for a total of $75.00
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
"eswar" <eswar@discussions.microsoft.com> wrote in message
news:8784CF3D-FE34-4C31-B4C9-65288970F236@microsoft.com...
> hi gerard,
> thnks for that. i have already set up that standard cost. wht i want is :
> every time that resource is used there is some additional cost incurred.
> like
> burden. i want that cost to be included in the budget. is there a way for
> that?
>
> regards
> Eswar
>
> "Gérard Ducouret" wrote:
>
>> Eswar,
>> To manage Material resource cost, don't use the "Cost per use" field but
>> the
>> simple "Std. Rate".
>> For example : Resource name = Concrete
>> Material label : Metric Ton
>> Std. Rate: 50$ (means 50$ / Metric ton)
>>
>> If you assign this resource on a task : units = 2 (2 Metric tons)
>> Project will calculate the material cost : 2 x 50 = 100 $
>>
>> Hope this helps,
>> --
>> Gérard Ducouret [Project MVP]
>>
>> "eswar" <eswar@discussions.microsoft.com> a écrit dans le message de
>> news:33748A68-BD9B-45AA-A3DC-29C4347EE9A8@microsoft.com...
>> > hi,
>> > i got a situation. i have a pool of material resources. these materials
>> have
>> > some standard cost on each unit being used. so i defined per use cost
>> > for
>> > each for them. but for some task if i use 2 units of that material
>> resource,
>> > then the per use cost is accounted for only one unit.
>> >
>> > is there a way by which i can calculate the peruse cost for each unit
>> > of
>> > material resource being used?? someone pl help me out..
>> >
>> > thnx & regards
>> > Eswar
>>
>>
>>