If a task is completed, is it possible to hide the task so that it no longer
shows when printing the programme, but is still there in order to show a full
programme when needed or to use again?

Re: Completed tasks by Mike

Mike
Wed Oct 27 05:32:34 CDT 2004

Hi Sarah,

Not directly possible. You could make the font and the bar colour white.
You could put a page break before and after the task and throw away the
blank page.

Mike Glen
MS Project MVP

Sarah A wrote:
> If a task is completed, is it possible to hide the task so that it no
> longer shows when printing the programme, but is still there in order
> to show a full programme when needed or to use again?




Re: Completed tasks by JamesG

JamesG
Wed Oct 27 07:41:02 CDT 2004

Sarah,

You "hide" tasks that have been completed, via applying a filter called:
Incomplete Tasks. You then print as normal.

James.G

"Mike Glen" wrote:

> Hi Sarah,
>
> Not directly possible. You could make the font and the bar colour white.
> You could put a page break before and after the task and throw away the
> blank page.
>
> Mike Glen
> MS Project MVP
>
> Sarah A wrote:
> > If a task is completed, is it possible to hide the task so that it no
> > longer shows when printing the programme, but is still there in order
> > to show a full programme when needed or to use again?
>
>
>
>

RE: Completed tasks by gordonrafPANTS

gordonrafPANTS
Wed Oct 27 07:45:08 CDT 2004

if I understand you correctly:
Filter the % complete column
Do this by:
Project/filtered for:.../ensure autofilter (bottom option) is selected.
On drop down arrow for the %complete column, select (custom)
filter for where value [does not equal] [100%]
This should hide all completed tasks, should you wish to see them again:
On drop down arrow for %complete, select (all).

Hope this is what you were after,
all the best,
G


"Sarah A" wrote:

> If a task is completed, is it possible to hide the task so that it no longer
> shows when printing the programme, but is still there in order to show a full
> programme when needed or to use again?

Re: Completed tasks by Mike

Mike
Wed Oct 27 11:40:52 CDT 2004

Duh! - I wasn't thinking filters:(

Mike Glen
Project MVP

Gordon Blair wrote:
> if I understand you correctly:
> Filter the % complete column
> Do this by:
> Project/filtered for:.../ensure autofilter (bottom option) is
> selected. On drop down arrow for the %complete column, select (custom)
> filter for where value [does not equal] [100%]
> This should hide all completed tasks, should you wish to see them
> again: On drop down arrow for %complete, select (all).
>
> Hope this is what you were after,
> all the best,
> G
>
>
> "Sarah A" wrote:
>
>> If a task is completed, is it possible to hide the task so that it
>> no longer shows when printing the programme, but is still there in
>> order to show a full programme when needed or to use again?




RE: Completed tasks by SarahA

SarahA
Mon Nov 01 04:29:02 CST 2004

Many thanks - I will try this today.

"Gordon Blair" wrote:

> if I understand you correctly:
> Filter the % complete column
> Do this by:
> Project/filtered for:.../ensure autofilter (bottom option) is selected.
> On drop down arrow for the %complete column, select (custom)
> filter for where value [does not equal] [100%]
> This should hide all completed tasks, should you wish to see them again:
> On drop down arrow for %complete, select (all).
>
> Hope this is what you were after,
> all the best,
> G
>
>
> "Sarah A" wrote:
>
> > If a task is completed, is it possible to hide the task so that it no longer
> > shows when printing the programme, but is still there in order to show a full
> > programme when needed or to use again?

Re: Completed tasks by SarahA

SarahA
Mon Nov 01 04:29:02 CST 2004

Thank you.

"James G" wrote:

> Sarah,
>
> You "hide" tasks that have been completed, via applying a filter called:
> Incomplete Tasks. You then print as normal.
>
> James.G
>
> "Mike Glen" wrote:
>
> > Hi Sarah,
> >
> > Not directly possible. You could make the font and the bar colour white.
> > You could put a page break before and after the task and throw away the
> > blank page.
> >
> > Mike Glen
> > MS Project MVP
> >
> > Sarah A wrote:
> > > If a task is completed, is it possible to hide the task so that it no
> > > longer shows when printing the programme, but is still there in order
> > > to show a full programme when needed or to use again?
> >
> >
> >
> >