MS Project Professional 2003

I have a master list that I use as a resource pool that sub projects linked
to, to utilize the resources. My problem is that when one of my Project
Managers changes the duration of a resource the percentage of units gets
skewed. How do I avoid this from happening. Is there a option that is on
that should be off or what exactly?

Re: Changing resource percentage by Gérard

Gérard
Mon Feb 26 11:10:07 CST 2007

Gary,

Have a look at the excellent Mike's Web site:
http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=320
Hope this helps,

Gérard Ducouret

"Gary" <Gary@discussions.microsoft.com> a écrit dans le message de news:
3648F1F6-A577-4987-9A16-35B2F7A140FD@microsoft.com...
> MS Project Professional 2003
>
> I have a master list that I use as a resource pool that sub projects
> linked
> to, to utilize the resources. My problem is that when one of my Project
> Managers changes the duration of a resource the percentage of units gets
> skewed. How do I avoid this from happening. Is there a option that is
> on
> that should be off or what exactly?