Dale
Mon Jul 03 09:53:20 CDT 2006
Meena --
In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question, do
the following:
1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Options
4. Select the View tab, if necessary
5. Set the Symbol value in the "Currency Options" section
6. Click OK
7. Save and close the Enterprise Global file
8. Ask all your PM's to exit and relaunch Microsoft Project Professional
Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"NewsGroup" <menna@chellasoft.com> wrote in message
news:ugYvx4onGHA.4716@TK2MSFTNGP02.phx.gbl...
>I would like to use the same currency symbol throughout every project plan.
> How to change the currency symbol in the Enterprise Global?
>
> Meena
>