Re: How do I Change my forecasted start dates when work doesn't be by JulieS
JulieS
Thu Jun 08 12:39:22 CDT 2006
Hi Oimate,
You are most welcome and thanks for the feedback. Do post again with
any further questions.
Julie
"Oimate28" <Oimate28@discussions.microsoft.com> wrote in message
news:9DB2F671-8D91-4A69-83F7-AA01A118E1A7@microsoft.com...
> Yes. That is very helpful! Thanks.
>
> "JulieS" wrote:
>
>> Hi Oimate28,
>>
>> You are most welcome and thanks for the feedback. I'm glad you are
>> finding the newsgroup helpful :-)
>>
>> To your questions:
>>
>> The idea of "forecasted dates" in Project is actually two-fold. Once
>> you have created your plan, you should save a Baseline (Tools >
>> Tracking
>> > Save baseline). The baseline is a copy of the start, finish,
>> duration, cost, and work as planned. That information (Baseline)
>> does
>> not change unless you re-baseline the project or tasks.
>>
>> Once you begin to supply actual data to project through tracking, the
>> dates in the Start and Finish fields may change. For example: you
>> originally planned a task for 3 days duration. In tracking the task
>> you
>> have already worked 2 days in actual duration and your resources
>> realize
>> that instead of 1 day in remaining duration, they actually have 2
>> days
>> remaining before the task will be complete. By updating the
>> remaining
>> duration to 2 days, Project will forecast the new Finish date, which
>> (assuming the task has a successor) will change the schedule of the
>> next
>> task. In my opinion, that is precisely what should happen. The
>> baseline data has not changed and we now have Variance (Duration
>> Variance, Finish Variance, Work, and Cost Variance).
>>
>> To your second question: Constraints seem to have a somewhat bad
>> reputation. I agree, in part, that constraints may be a sign of
>> "weakness" in the schedule but usually only because people use
>> constraints instead of links (predecessors and successors) to drive
>> the
>> schedule. Constraints such as those imposed by the Reschedule
>> Uncompleted Work command are not, in my opinion, a sign of weakness,
>> but
>> rather a reflection of reality. We were supposed to start this task
>> on
>> 5/8 but due to circumstances, we cannot start until 6/9. If you
>> waited
>> to reflect the change in start until you actually started the task
>> (by
>> entering an Actual Start date), you have potentially lost the time
>> needed to make adjustments to the revised schedule to meet your
>> deadlines.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>>
>>
>> "Oimate28" <Oimate28@discussions.microsoft.com> wrote in message
>> news:40C78BA0-AD35-404C-9905-94201D44A241@microsoft.com...
>> > Thanks to you both for your responses. I love this discussion
>> > forum.
>> > I
>> > guess my question is 2 parts. 1st part asks about the principle /
>> > philosophy
>> > of project forecasted dates. I have heard that you should never
>> > change
>> > forecasted dates in project. Is this true? If it is not true,
>> > then I
>> > have a
>> > question about Jules suggestion. Jules, I followed your
>> > instructions
>> > to
>> > update the forecasted start date from 5/8 to 6/9, but when I do
>> > this,
>> > I get a
>> > constraint icon in the information column. I have been trained
>> > that
>> > any
>> > constraint icons are an indication of weaknesses in the schedule.
>> > What are
>> > your thoughts? Thank you so much for your earlier feedback. I
>> > have
>> > been
>> > looking for a resource to help me learn the true fundamentals of
>> > project so I
>> > can learn to manage a project from a foundational sound project
>> > schedule. I
>> > have been in over my head in the past on Project.
>> >
>> > "JulieS" wrote:
>> >
>> >> Hi Oimate28,
>> >>
>> >> You could use the Tools > Tracking Update Project > Reschedule
>> >> Uncompleted Work to start after to change the projected start date
>> >> of
>> >> all tasks not marked 100% complete.
>> >>
>> >> I hope this helps. Let us know how you get along.
>> >>
>> >> Julie
>> >>
>> >> "Oimate28" <Oimate28@discussions.microsoft.com> wrote in message
>> >> news:4DED804C-2F8A-4DE5-B980-9DF0F790D74E@microsoft.com...
>> >> >I have a project task forecasted to start on 5/8, but work has
>> >> >been
>> >> >delayed
>> >> > and will not start until 6/9. Should I leave the forecasted
>> >> > date
>> >> > alone and
>> >> > put in an actual start date when work has begun? Or should I
>> >> > change
>> >> > the
>> >> > forecasted start date, knowning it has not yet beguN?
>> >>
>> >>
>> >>
>>
>>
>>