Dale
Fri Feb 23 09:20:24 CST 2007
Paul --
You are more than welcome, my friend! :)
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Paul Goldmann" <paul.goldmann@msn.com> wrote in message
news:uWJaVJzVHHA.4632@TK2MSFTNGP04.phx.gbl...
> Great Feedback, Thanks!
>
> --
> Paul Goldmann
> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> schrieb
> im Newsbeitrag news:uqC7MMrVHHA.1016@TK2MSFTNGP04.phx.gbl...
>> Paul --
>>
>> If I understand the issue correctly, you want to set every Friday as a
>> non-working day for one particular resource, right? If so, here's how:
>>
>> 1. Apply the Resource Sheet view and double-click the name of the
>> resource in question.
>> 2. Click the Change Working Time button.
>> 3. In the Change Working Time dialog, select the Work Weeks tab
>> 4. Click the Details button
>> 5. In the Details dialog, select Friday
>> 6. Select the "Set days to nonworking time" option and click OK.
>> 7. Click OK to close the Change Working Time dialog.
>> 8. Click OK to close the Resource Information dialog.
>> 9. Save your project.
>>
>> Hope this helps.
>>
>> --
>> Dale A. Howard [MVP]
>> Enterprise Project Trainer/Consultant
>>
http://www.msprojectexperts.com
>>
http://www.projectserverexperts.com
>> "We wrote the book on Project Server"
>>
>>
>>
>> "Paul Goldmann" <paul.goldmann@msn.com> wrote in message
>> news:eqqo5wpVHHA.4964@TK2MSFTNGP06.phx.gbl...
>>> Hi Dale,
>>>
>>> Yes, I know. But in previous versions I could select the row header for
>>> example for Friday and set this as free, BUT now I have to enter a start
>>> and end date for the calendar exception and I do not want to limit the
>>> exception to dedicated time period.
>>>
>>> Thanks again
>>> Paul
>>>
>>> --
>>> Paul Goldmann
>>>
>>> "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com>
>>> schrieb im Newsbeitrag news:ejU4oUpVHHA.4404@TK2MSFTNGP03.phx.gbl...
>>>> Paul --
>>>>
>>>> Navigate to the Resource Sheet view and double-click the name of the
>>>> resource in question. On the General page, click the Change Working
>>>> Time button. Hope this helps.
>>>>
>>>> --
>>>> Dale A. Howard [MVP]
>>>> Enterprise Project Trainer/Consultant
>>>>
http://www.msprojectexperts.com
>>>>
http://www.projectserverexperts.com
>>>> "We wrote the book on Project Server"
>>>>
>>>>
>>>>
>>>> "Paul Goldmann" <paul.goldmann@msn.com> wrote in message
>>>> news:u1PSa2mVHHA.1120@TK2MSFTNGP02.phx.gbl...
>>>>> Hi,
>>>>>
>>>>> in former versions of Project I could for example declare Friday as
>>>>> non working in a resource calendar. In Project 2007 I cannot find this
>>>>> option.
>>>>>
>>>>> Any idea?
>>>>>
>>>>> Thanks Paul
>>>>>
>>>>> --
>>>>> Paul Goldmann
>>>>>
>>>>
>>>>
>>>
>>>
>>
>>
>
>