Re: Change Resources Calendar by Kilen
Kilen
Thu Oct 26 14:47:01 CDT 2006
Thanks, that worked! That's what I like about this Discussion Group...it
gives you great guidelines and solutions!
Kilen
"Guidho" <"hoet AT guidance DOT be" wrote:
> Two options do accomplish this:
> - Create a new base calendar (8am-12pm, 1pm-5pm) and apply this base
> calendar as the new base calendar for the resource
> - In the resource calendar, select the day headers (not individual days)
> and change his working hours. You can do this by entering 8am-12pm,
> 1pm-5pm, or by simply clicking 'use default'.
>
> Hope this helps,
> Guidho
>
>
> Kilen wrote:
> > I have a resource that has his available time set to weekdays from 10am to
> > 12pm, using our company's base calendar. I'm trying to change him back to
> > having 8 hours per day, 8am-12pm, 1pm-5pm, but I can't seem to find a way
> > without going day by day and making the change. I feel like I'm missing
> > something, that it should be easy enough to just "reset" his calendar 8 hours
> > a day.
> >
> > Thx!
>