I have a schedule with custom fields. I enter a start date into Start1. I
then calculate the duration1 field based on info in two other fields, (units
per day / # of days) and calculate Finish1. My Gantt bars are set up to
display these fields and it works fine. What I cannot do is right click on
the task bar to split the task. It appears to work as I try to drag the split
to where I want it but when I try and drop the split where I want it nothing
happens. Is it because I am calculating these fields?

Re: Can't split task by Jan

Jan
Fri Sep 08 12:35:26 CDT 2006

Hi,

Splitting the task will mobve finish but not the calculated fields.
They are CUSTOM fields meaning that they are yours and Project doesn't
calculate them.

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"BB" <BB@discussions.microsoft.com> schreef in bericht
news:D4EFB2FA-9BA1-41CB-8333-D351E91A38E0@microsoft.com...
> I have a schedule with custom fields. I enter a start date into Start1.
I
> then calculate the duration1 field based on info in two other fields,
(units
> per day / # of days) and calculate Finish1. My Gantt bars are set up to
> display these fields and it works fine. What I cannot do is right click
on
> the task bar to split the task. It appears to work as I try to drag the
split
> to where I want it but when I try and drop the split where I want it
nothing
> happens. Is it because I am calculating these fields?