RE: Cannot enter actuals in Web Access by anonymous
anonymous
Mon Aug 23 00:30:35 CDT 2004
Hi Mark,
In case you wanted to enter the actuals in Hrs in your
existing project (Which was published before doing the
settings in PWA as i have told u earlier), Please RE
PUBLISH the assignments.
If you publish a plan before doing the settings (As told
by me earlier) in PWA then you have to RE PUBLISH it, in
order to fill the actuals in Hrs)
After Re Publishing the assignment, you will be able to
enter the actual work as you are able to fill in Dummy
Plans.
RISHI SHARMA
>-----Original Message-----
>Hi Mark,
>
>You are facing this problem because you must have
>published this proeject before doing the settings in
PWA's
>ADMIN part.
>
>Tracking Settings (In ADMIN --> Customize Microsoft
>Project Web Access --> Tracking Settings) are required
>BEFORE PUBLISHING A PROJECT PLAN IN EPM'S NEW SERVER.
>
>You have to select (Under "Specify the default method for
>reporting progress on tasks") - the radio button of
>"Hours of work done per day or per week: Resources report
>the hours worked on each task during each time period"
>before publishing any Project Plan.
>
>In case of any confusion please get back to me.
>RISHI SHARMA
>(rishi.sharma@churchill.com)
>
>
>>-----Original Message-----
>>Unfortunately, I have the same problem!!! I need the
same
>advice as you. I am
>>afraid this is a limitation associated with using
>the "web" client. I wish
>>someone would clarify the situation.
>>
>>"Mark Etheridge" wrote:
>>
>>> Hello,
>>>
>>> We are trying to implement EPMS and so I have added a
>project to the project
>>> server 2003 (EPMSimplement.mpp). I have been
>configuring the settings within
>>> EPMS. One problem that I am having is that we cannot
>enter in 'Actuals' in
>>> timesheet view. We can only adjust the % complete, and
>remaining work
>>> columns. I have been adjusting the setting within
>the "Customize Probject
>>> Web Access" within the Admin center. I have tried all
>options, including the
>>> 'Managed Periods' option where you open reporting
>periods. Nothing seems to
>>> work with this project. This project file was added to
>project server when
>>> the project was 50% complete. So there are no actuals
>added for the first
>>> half of the tasks. Would this have something to do
with
>my problem? Does
>>> anyone have any options that I can try to hopefully
>resolve?
>>>
>>> I have added a few other 'dummy' projects, and we can
>enter 'actuals' to the
>>> tasks from these projects.
>>>
>>> Mark
>>>
>>>
>>>
>>.
>>
>.
>