mikejw
Fri Oct 07 14:23:01 CDT 2005
Thanks Mike & Dave,
Since I've already created this schedule, is there any way of preventing
Project from changing the durations and dates when I change the hours on the
calendar in "Tools, Change Working Time"? I'm guessing that going from a 8
hour day to a 10 hour day is going to bring my end date back and show me a
higher slack value. Would making all current tasks "Fixed Duration" work?
If not, I'm assuming I would need to make a copy of the project prior to the
calendar changes so that I could revise the durations upward based on the
original dates so as to get the dates back to where they were previously.
Does this seem correct?
"Mike Glen" wrote:
> Hi Mike,
>
> Welcome to this Microsoft Project newsgroup :-)
>
>
> You're on the right track. You must get the calendar and working hours set
> correctly. If in doubt have a quick check here: FAQ Item: 5. Default
> Working Hours.
>
> Then you can get on with assigning resources. If you only have one resource
> per task (the ideal), then effort driven doesn't come into play. Indeed, if
> you assign multiple resources to a task AT THE SAME TIME, you can also
> forget about effort driven. Effort driven settings only come into effect if
> you change the assignments. Otherwise, press on and good luck!
>
> FAQs, companion products and other useful Project information can be seen at
> this web address:
http://www.mvps.org/project/
>
> Hope this helps - please let us know how you get on :-)
>
> Mike Glen
> Project MVP
>
>
> mikejw wrote:
> > I work on a project that uses MS Project 2003 Standard and we have a
> > developed a schedule (time only, no resources or cost) based on
> > historical data (they have done this many times before) where they
> > know a certain number of people will be needed on the various tasks.
> > They want to add these resources (people) to get an idea of who and
> > when they will be needed, as well as seeing where someone might be
> > overallocated. All tasks are currently in the schedule as "fixed
> > units", non effort-driven.
> >
> > All tasks are currently on a 6 day/8 hr work week and I've been asked
> > to change the calendar to a 6 day/10hr day calendar. I've added the
> > resources to a resource pool all at 100% and need to begin assigning
> > people to tasks (although not all tasks will have a resource
> > associated with it).
> >
> > Can someone provide my next steps? My thought is that I should
> > change the current calendar through "Tools, Change Working Time" to a
> > 6 day/10 hr day calendar and then change the base calendar on the
> > resource sheet to the same. Since I want the durations to remain the
> > same throughout the schedule, will making these changes to the
> > calendars affect my current durations and dates? Also, would I need
> > to change each task that will have a resource assignment to a "fixed
> > duration", non effort-driven task?
> >
> > Any help is greatly appreciated.
>
>
>
>