Steve
Sun Oct 09 06:38:07 CDT 2005
There are a bunch of things to keep in mind.
1: Durations are always calculated and stored in minutes. The Calendar
Options "hours per day" entry sets the conversion between the actual minutes
of duration and the number of "days" displayed. So if a task is done by one
resource on each of three shifts so it starts Monday at 8am, is worked on
continuously for 3 shifts, and ends Tuesday at 8am, and the "hours per day"
setting is the default 8 hours, that task is taking place over 24 working
time hours and will display its duration as "3 days."
2: Duration is the number of working time minutes, that is, minutes of the
day when work could legally be scheduled, between when the task begins and
when it ends, regardless of whether work actually will take place during
each minute. When you have more than one resource on the task, the duration
is the time between the earliest starting resource begins and the latest
finishing resource ends. Try this experiment with all settings and calendars
on the out-of-box defaults. Create a 1 day duration task X and 2 resources,
Joe and Bill, with the project starting on a Monday. Assign both resources
to the task. Duration 1 day. Make Monday a non-working day for Bill.
Duration changes to 2 days, task starts Mon 8am and ends Tue at 5pm,
reflecting Joe does his half on Monday and Bill does his on Tuesday. Make
Tues and Wed also non-working days for Bill. Task now starts Mon at 8am and
ends Thur at 5pm but the duration is STILL 2 days because on the calendar
governing Bill's part of the work, those days are not potential working time
and so don't count towards the duration value. Now try it again but instead
of adding non-working days to Bill's calendar, after you add Joe and Bill to
the 1 day task, change Bill's work shift to be swing shift with working
hours of 15:00-19:00 and 20:00-00:00. Now the task begins Mon 8am and ends
Mon at midnight. Now the duration shows 1.75 days, reflecting that the 2
days of total work, 1 day for each resource, overlap (The fact that several
minutes of work might be getting done during each minute on the clock during
the overlap doesn't matter - a working time minute is 1 duration minute
regardless of how many resources are on the job during it.)
3: You absolutly need to group your resources by shift. If I have 3 guys
covering 3 shifts, that should be listed as 3 entries "DayShiftWorker -
100%", "SwingShiftWorker - Max 100%", and "GraveyardWorker - Max 100%" each
with the appropriate resource calendar describing his shift hours and NOT
"Workers - 300%" with a 24-hour calendar. The latter way means that there
are three workers who work together the same hours, a task can use 1 2 or
all 3 of them, their working hours are 24/7 so each of them individually
never takes a day off, never has a lunch break, etc and so even if I only
assign 1 of them, once work on a task begins it will proceed without
interuption until it ends, no matter how long it takes. If Joe is one of
the group and I assign him to a 2 week task, he works without even a single
minute off and doesn't see the light of day or get even the shortest rest
break for 2 solid weeks. (This is why I'm so opposed to using the 24 hour
calendar as the project calendar or for any resources except automated
machinery that really does work like that - humans always get time off and
the calendars that control tasks should always reflect that reality - the 24
hour calendar doesn't allow any time off at all.)
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
"snetzky" <snetzky@yahoo.com> wrote in message
news:1128711476.199938.286950@g43g2000cwa.googlegroups.com...
>I appreciate the feedback and help. I'll probably shoot you a copy
> after work today, Part of the problem may be that I'm not running a
> normal calendar and Project may be trying to compensate somehow in a
> way that I'm not catching.
>
> In the meantime, I've changed all of my resources to be either on a 12
> hour day or 12 hour night shift. Do I need to tell my tasks to use one
> or the other, or can I leave them on a 24 hour schedule?
>
> Larry
>