Hi,
Why would you calculate that? Project does it for you.
Assign the resource to the task
Gantt Chart, Window menu, Split
In the foem below
set task type to fixed duration
fill in the right diuration
fillin the amount of work
Click OK
HTH
--
Jan De Messemaeker
Microsoft Project MVP
http://users.online.be/prom-ade
"Atle" <Atle@discussions.microsoft.com> wrote in message
news:78179E42-8942-40ED-9DEC-AF495873CBFB@microsoft.com...
> Hello,
>
> Please consider the following:
>
> One task is set to work for 20 hrs. The duration is set for 2 weeks (80
> hrs). How can I calculate how many % (answer: 25%) of this resource's time
> will be spent on this task over the 2 week period ?
>
> Thanks a lot!