John
Sat Feb 24 09:59:17 CST 2007
In article <3131869A-23AD-45C3-A902-116B1F395FE1@microsoft.com>,
Adel <Adel@discussions.microsoft.com> wrote:
> thank you for your reply
>
> sorry, I may miss typed what I want !
>
> I need to calculate the planned % complete for project ,summary tasks and
> tasks in project.
>
> I have neither cost or resources assigned to each task.
Adel,
This may seem like a dumb question but how can you have a "planned" %
complete if there are no resources working on the tasks?
John
Project MVP
>
>
> "Mike Glen" wrote:
>
> > Hi Adel,
> >
> > Welcome to this Microsoft Project newsgroup :)
> >
> > Project will calculate this for you when you enter Actual Work and
> > Remaining
> > Work for each task.
> >
> > FAQs, companion products and other useful Project information can be seen
> > at
> > this web address:
http://project.mvps.org/faqs.htm
> >
> > Hope this helps - please let us know how you get on :)
> >
> > Mike Glen
> > MS Project MVP
> > See
http://tinyurl.com/2xbhc for Project Tutorials
> >
> >
> > Adel wrote:
> > > I need to calaculate the planned % complete for project and tasks
> > > inside the project.
> > >
> > > I have cost and resources assigned to each task.
> > >
> > > any help
> >
> >
> >
> >