Mike
Wed Jul 07 04:47:37 CDT 2004
Hi Deluth,
That's exactly what Deadline dates are for! Don't type in dates, but set a
deadline (Task Information/Advanced tab) and see where the milestone will
occur according to the Durations and logic of its Predecessors. If the
scheduled date becomes before the milestone, then you have some leeway in
your plan. On the other hand, if the milestone is beyond the Deadline date,
then Project will tell you with an warning icon in the Indicator column, and
you can then re-adjust your plan until it shows you should meet the Deadline
date set. This way you will be modelling what is possible rather than
planning to meet an impossible milestone.
Mike Glen
Project MVP
"Deluth" <Deluth@discussions.microsoft.com> wrote in message
news:4DDF0BF5-45F4-465D-8CAA-300409B28B6B@microsoft.com...
> Jan - I am not looking to set this for the entire project. I just have a
few milestones that I need "on-the-fly" calculations of dates. Yes, I am
entering the dates directly onto the milestones. I sometimes have to work
out the constraint given to me via a release date and the constraints given
via features of the project. If it's date driven, I want to drive the
milestones backwards to find what features cannot be completed by the given
date. If it's feature driven, I want to drive forwards to find out what
date will the project completes - based on the milestones. Hope this
clarify things.
>
> "Jan De Messemaeker" wrote:
>
> > Hi,
> >
> > Sorry John, but Project DOES do this simultaneously.
> > When you calculate from Project Start, Late Start and Late Finish give
the
> > result of the backward calculation, and Total Slack the difference
between
> > the two.
> > No need to change the option.
> >
> > HTH
> > --
> > Jan De Messemaeker
> > Microsoft Project Most Valuable Professional
> >
http://users.online.be/prom-ade/index.htm
> > 32-495-300 620
> > "John" <mjensen@theriver.com> schreef in bericht
> > news:mjensen-428D4D.20102105072004@msnews.microsoft.com...
> > >
> > > Deluth,
> > > It is not clear what exactly you are trying to accomplish. Project
plans
> > > can be set up basically one of two ways but not both simultaneously.
> > > They can either be forward scheduled or reverse scheduled. In the
first
> > > case (the default), the Project Start date is set (Project/Project
> > > Information, Start date) and everything is scheduled from that date.
In
> > > the second case the Project Finish date is set (Project/Project
> > > Information, Finish date and "schedule from" is set to "Project finish
> > > date")) and everything is scheduled in reverse from that date.
> > >
> > > Each person has their preferred way of setting up a schedule plan. I'm
a
> > > forward scheduler myself. I set up the plan with all tasks linked in a
> > > logical sequence and an estimated duration for each task. If the end
> > > date meets the required date of the completion milestone, everything
is
> > > great. Most likely however, the end date will be beyond the completion
> > > milestone. I then either set a Deadline milestone or simply put a
> > > "finish no later" constraint on my completion milestone and display
the
> > > "Total slack" field to see how much schedule I need to make up by
> > > rearranging the plan or adding workaround tasks if the slip occurs
after
> > > the plan is started.
> > >
> > > Hope this helps.
> > > John
> >
> >
> >