Steve
Wed Jan 05 16:36:59 CST 2005
Sort of ... you still have to tell Project how many hours of OT he's
working, it doesn't do it automatically based on the calendar. But if you
display the Actual Overtime Work row in the usage view and put in 2 hours OT
and 10 hours work, that means he did 8 hours straight time and 2 hour OT and
the costs will be figured accordingly.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
"Stefan Robert" <srobert.DELETEME@b2b2c.ca> wrote in message
news:2005010512264716807%srobertDELETEME@b2b2cca...
> Hello everyone,
>
> is there a way to make MS-Project calculate overtime automatically.
>
> If I have a resource that I defined that can work 7 hours a week, when he
> works 8 hours can MS-Project calculate 1 hour of overtime automatically?
> If so how can I make MS-Project do this?
>
> Thanks
>
> Stéfan
>