Mike
Fri Mar 21 09:47:04 CDT 2008
You're welcome, Rachel :-)
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
"Rachel" <Rachel@discussions.microsoft.com> wrote in message
news:05812F7B-9EC7-4BFD-B01D-306C2CC04B55@microsoft.com...
> Thank you. That was very helpful.
>
> "Mike Glen" wrote:
>
>> Hi Rachel,
>>
>> Welcome to this Microsoft Project newsgroup :)
>>
>> The Baseline Cost field shows the cost of the project when the schedule
>> has
>> just started (assuming you activate Baselining), based on the hours of
>> Work
>> * Cost Rate for each of the assignments, plus any fixed cost - ie it is
>> the
>> expected or planned cost. Whereas the Budget Resource is the amount of
>> cash
>> that has been allocated for the project (hopefully a greater figure to
>> allow
>> for cost escalation!). Try reading Help for Budget Resource.
>>
>> Fixed costs are those that do not depend on the hours of work of the
>> resources. Yes, they would include rent and hire fees, possibly
>> overheads
>> for the project, one-off payments for hire of plant (like a crane could
>> have
>> a fixed cost £1000 for its use plus £100 per day). Another use could
>> be for
>> where part of the project is contracted out for a fixed fee, in which
>> case
>> you would not track individual resource costs. How you use fixed costs
>> is a
>> matter of opinion. An advantage with creating a task for rent is that it
>> can be kept separate from the work. Make a milestone for the rent, or
>> insert a recurring task with nil work and assign the rent to it. Or you
>> could add the monthly rent to the tasks that creates its need.
>>
>> FAQs, companion products and other useful Project information can be seen
>> at
>> this web address:
http://project.mvps.org/faqs.htm
>>
>> Hope this helps - please let us know how you get on :)
>>
>> Mike Glen
>> MS Project MVP
>> See
http://tinyurl.com/2xbhc for Project Tutorials
>>
>>
>>
>> "Rachel" <Rachel@discussions.microsoft.com> wrote in message
>> news:CA3DAFDD-BD07-404C-BBAA-7EDDD95128F3@microsoft.com...
>> >I am just starting to configure MS Project 2007 and have a few
>> >questions.
>> >
>> > What is the difference between a budget resource and the baseline cost?
>> > What
>> > is the advantage of using the budget resource if you are entering
>> > baseline
>> > costs?
>> >
>> > What type of tasks do you assign fixed costs to? For example, rent. It
>> > is
>> > a
>> > monthly recurring cost that is not dependent on task usage or schedule.
>> > Should I create a seperate set of monthly tasks in order to incurr the
>> > cost
>> > of rent in our project?
>> >
>> > I appreciate any suggestions.
>> >
>> > Thanks.
>>
>>
>>