RE: Baseline compare by ChrisMarriott
ChrisMarriott
Mon Oct 31 11:06:45 CST 2005
Bobby
The baseline is the only comparison of the project schedule at the beginning
of the project unless you have another copy of the project plan. If you dont
then project copies the actual fields into the schedulefd fields or vice
versa depending on your tracking method
If you do have a copy of the original plan then use the compare projects
toolbar to check for variances
Hope this helps
--
Regards
Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
"Bobby McCally" wrote:
> I have received Project schedules. But, it does not appear they have created
> baseline(s) nor statused the updates. Can I compare one updated schedule to
> another, even if no baseline was created? I am most interested in gantt bar
> comparison like one would do had a baeline been created.