> I baselined my schedule and we were working right along until a change in
> approach means a replan. I only need to replan certain tasks. What is the
> easiest way to rebaseline the schedule?
>
> Thank you,
Londa Sue,
If you don't need to keep the original baseline on the changed tasks,
select the changed tasks and save the baseline for just those selected
tasks (that's one of the options in the Save Baseline window). If for
some reason you want to retain the complete original baseline, select
Baseline1 from the selection box in the Save Baseline window and then
save a new baseline for the entire project.
Hope this helps.
John