Jan
Mon Jul 03 08:53:12 CDT 2006
Hi Steve,
You're more than probably right.
I thought he was installing the 10 computer through the task, such that they
were material resources.
Greetings,
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"Steve House" <sjhouse.remove@remove.hotmail.com> schreef in bericht
news:OnVfawpnGHA.4636@TK2MSFTNGP03.phx.gbl...
> Yes, you can assign material resources but the scenario you posed in your
> question is NOT one of assigning of material resources. A material
resource
> is an item that is either a: incorporated into the final deliverable; or
b:
> is consumed by the activity of creating that deliverable. Your computers
> doesn't fit into either caregory. If your project was to install POS
> terminals in a chain of retail stores and the 10 computers were the actual
> terminals that you're installing for delivery to the customer, then they'd
> be material resources. Fuel to operate a generator needed to power those
10
> computers while people worked with them in a remote location without
regular
> power would be a material resource because it's used up by the activity.
> But in the scenario you're describing those computers are WORK resources,
> not materials, as is the case with most tools, etc. Their availability
> drives the schedule just like a computer operator's availability does.
> Enter them into the resource list as "Computers", type - work,
> availability - 2000% to indicate 20 computers in the group. If you need 5
> computers for a task, assign "Computers" to it at 500% and that will leave
> 15 available for other things. The name will turn red indicating
> overallocation if at any time you have more than 20 computers assigned to
> use.
>
> --
> Steve House [Project MVP]
> MS Project Trainer & Consultant
> Visit
http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "NewsGroup" <menna@chellasoft.com> wrote in message
> news:u91KGImnGHA.1592@TK2MSFTNGP04.phx.gbl...
> > We can assign human resources to a project.
> > Is it possible to have an accout of the material resources available and
> > allocate them to projects?
> > (eg)I have 20 computers available.
> > I need 10 computers for 1 task.
> > Is it possible to assign materia; resources as we do for human
resources?
> >
> > Meena.
> >
>