Coen
Thu Jul 05 06:50:00 CDT 2007
Thanks Steve for your answer, sorry for this late reaction...,
I was hoping for a method to assign both a material resource (soil) and
equipment to the task in such a way that Project calculates the duration of
the task. I'd like to vary my equipment (amount and production rate)in the
resource pane so I can optimise my project by just changing the standard
production rate of a cane. Now I need for each task to calculate the duration
myself.
Ex.
Task:
Build a brick wall (fixed work);
Resources:
10.000 m2 bricks (Material resource)
Well experienced mason@2.000 bricks/day (Work resource) = 5 days
Junior mason@500 bricks/day = 20 days
In this way I can optimise the duration and costs of the project
Greetings,
Coen
"Steve House" wrote:
> Cranes would be an example of work resources. It wasn't clear in your post
> whether you are treating them presently as work resources or material
> resources but they are definitely NOT materials (materials are either
> consumed, used up, by the task or are incrporated into the task's
> deliverable). Create a resource named "Cranes" and assign a maximum
> availability equal to the number of cranes you have yimes 100%, ex. 5 cranes
> means there's a max availability of 500%. If ou assign 1 crane to a given
> task, assign it 100%, if you assign 2 assign "Cranes, 200%" and so forth.
> Make the tasks fixed work. Now if you estimate it will take 10 days to do a
> layer with 1 crane assigned, upping it to 2 cranes (edit 100% -> 200%) will
> halve the duration to 5 days.
>
> --
> Steve House [Project MVP]
> MS Project Trainer & Consultant
> Visit
http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Coen" <Coen@discussions.microsoft.com> wrote in message
> news:49A08547-F76A-429B-B7B8-DEFBB269888D@microsoft.com...
> > I've searched through several information sources and can't figure this
> > seemingly simple problem out;
> >
> > My project consists of covering up an area with several layers of soil
> > where
> > each layer has its own specifications and volume. To do this, we use
> > hydraulic cranes with a specific production speed per day (m3/d). The
> > layers
> > of soil (fixed work) are the tasks where I assign the specific soil types
> > to
> > (as material resources).
> >
> > Now I'd like to plan my project by assigning cranes with a fixed
> > production
> > rate (and price per day). Logically, by assigning more cranes the project
> > finishes earlier. Problem is that I can't seem to vary the amount of
> > cranes
> > per layer to see what the effect is on the project's finisching date.
> >
> > Only way to find out the duration of the project is to assign a variable
> > consumption rate to the material resource and fix the work. That way I
> > can't
> > easily change the amount of cranes and determine the extra cost.
> >
> > Thanks in advance
>
>