I have a list of tasks and time estimates for all of them....however we do
them out of order and I would like the end date of the project to recalculate
based on whats left for unfinished tasks....


is this possible?

Re: Adjust project completion date as tasks are completed by John

John
Fri Feb 23 17:18:49 CST 2007

In article <328991A9-D387-43B9-B35B-16A88BA3F850@microsoft.com>,
deepice <deepice@discussions.microsoft.com> wrote:

> I have a list of tasks and time estimates for all of them....however we do
> them out of order and I would like the end date of the project to recalculate
> based on whats left for unfinished tasks....
>
>
> is this possible?

deepice,
It sounds like you don't really have a schedule, just a list of tasks. I
assume they are all un-related. If so, then the project finish date will
be the finish date of the latest task. Is there something I'm missing?

John
Project MVP

Re: Adjust project completion date as tasks are completed by Gérard

Gérard
Fri Feb 23 17:22:24 CST 2007

Hello deepice
You are we doing the tasks out of order ? Strange project indeed...

Nevertheless, that's it's normal behavior : Project recalculate the finish
date of the project, based on what's left for unfinished tasks.



Gérard Ducouret


"deepice" <deepice@discussions.microsoft.com> a écrit dans le message de
news: 328991A9-D387-43B9-B35B-16A88BA3F850@microsoft.com...
>I have a list of tasks and time estimates for all of them....however we do
> them out of order and I would like the end date of the project to
> recalculate
> based on whats left for unfinished tasks....
>
>
> is this possible?



Re: Adjust project completion date as tasks are completed by Mike

Mike
Fri Feb 23 17:50:00 CST 2007

Hi deepice ,

Welcome to this Microsoft Project newsgroup :)

Have you tried Tools/Tracking/Update Project.../Reschedule unscheduled work
to start after:

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials


deepice wrote:
> I have a list of tasks and time estimates for all of them....however
> we do them out of order and I would like the end date of the project
> to recalculate based on whats left for unfinished tasks....
>
>
> is this possible?