I am trying to use the Adjust Dates button to advance an MS Project 2000;
however there appears to be a problem with some tasks which take place over
the weekend. I have created a calendar which I have called weekend and I have
made Saturday and Sunday the only working days and I have allocated the
appropriate tasks to this calendar. The problem is that when I look on the
Gannt Chart the weekends where there is work have not moved as predicted. I
am sure that I am doing something wrong, but I have only been using Project
for a couple of weeks.
Thanks in advance.

RE: Adjust Dates by JackDahlgren

JackDahlgren
Fri May 09 16:36:01 CDT 2008

Chris,

Take a look at your calendar and make sure the the weekends are there for
each month. Sometimes people make changes which do not go far enough into the
future and don't realize it.

-Jack Dahlgren

"Chris waller" wrote:

> I am trying to use the Adjust Dates button to advance an MS Project 2000;
> however there appears to be a problem with some tasks which take place over
> the weekend. I have created a calendar which I have called weekend and I have
> made Saturday and Sunday the only working days and I have allocated the
> appropriate tasks to this calendar. The problem is that when I look on the
> Gannt Chart the weekends where there is work have not moved as predicted. I
> am sure that I am doing something wrong, but I have only been using Project
> for a couple of weeks.
> Thanks in advance.
>