Re: Adding a resource in the middle of the task by Gerard
Gerard
Thu Jan 06 16:05:24 CST 2005
Hello,
MS Project (2002) works naturally that way :
If you enter a 50% progress on one task with one resource, then you add a
new resource, Project assigns the new ressource only on the remaining
duration.
Another way : you can enter the work one day by day basis in the Task Usage
view
Gérard Ducouret
"ssiegler" <scott_siegler@yahoo.com> a écrit dans le message de
news:1105047386.573680.295520@z14g2000cwz.googlegroups.com...
> Hello,
>
> I am somewhat new to MS Project. Is it possible to add a resource to a
> task after the task has already started. I was currently trying to use
> the personal calendar, but I dont want to turn days to non-working days
> that are prior to a resources start on a task because I want that
> resource working on another task. So, is it possible to add a resource
> and make that resource start doing work on a task in the middle of that
> task?
>
> thanks,
> Scott
>